Work to begin in 2027 on 6.25-mile power line in Youngstown, Campbell
Work on a $27 million power line project in Youngstown and Campbell will begin in November 2027 after the Ohio Power Siting Board gave permission to a FirstEnergy subsidiary for it. The board voted 6-0 Thursday during a meeting that lasted less than five minutes and included approval for three other projects elsewhere in the state. The board in May 2022 rejected the initial proposal from American Transmission Systems Inc. after more than 300 Mahoning Valley residents and elected officials opposed it because of high-tension lines going through the heart of downtown Youngs-town, ...