YOUNGSTOWN - The rehabilitation of a small bridge on South Avenue resulted in big headaches but is finally done.
A $1,635,232 project to the bridge that was supposed to be done by Sept. 28 was opened Friday on one of the city's busiest corridors.
After previous delays to even get the work started because of gas line relocation issues, the project started June 1 and was supposed to take 120 days. It ended up taking 173 days to complete.
Charles Shasho, the city's deputy director of public works, said: "It was a significant delay. Nearly two months is unacceptable."
But, Shasho said, it was unavoidable.
There were further complications with the Enbridge Gas Co. line that had to be put in a casing and installed under the bridge that goes over a Youngstown and Southeastern Railroad Co. train line, Shasho said. The railroad company also needed to sign off on the gas line.
The city's board of control awarded the contract May 8, 2025, to Marucci & Gaffney Excavating Co. of Youngstown. The city received a $1,065,900 state grant for the project.
Pavement markings were being finished Friday, Shasho said.
The closure of the small bridge, just south of the larger Peace Officers Memorial Bridge that crosses the Mahoning River, caused a 3-mile detour for those who drive on South Avenue. The pedestrian detour was 0.7 miles.
The work forced the closure of South Avenue between the Interstate 680 exit and Williamson Avenue.
The work included the rehabilitation of the bridge's substructure, refacing the abutments, replacing the approach slabs that connect the roadway pavement to the bridge as well as the guardrails, sidewalks, bridge railings, curbs and pavement markings.
The bridge was constructed in 1957 and had major rehabilitation work done to it in 1990. It underwent further improvement work in 2015.
Before this project, the bridge was listed as "poor" and "structurally deficient" by the Federal Highway Administration.
The FHA's National Bridge Inventory report stated the structure was "intolerable requiring high priority of corrective action" while the substructure had a loss of a section or deterioration.
The report added about the substructure: "Local failures are possible. Fatigue cracks in steel or shear cracks in concrete may be present."
Also, the bridge railings and guardrail did "not meet current acceptable standards or a safety feature is required and none is provided," according to the report.
Of Ohio's 29,960 bridges, about 5% are classified as structurally deficient.