CANFIELD -- The Canfield Local School District's facilities plans are now down to three options, ranging in cost from $91 million to $108 million.
A desired option could be presented to the board of education on April 19.
The estimated cost for Option A is $108 million. This would include the construction of a new K-4 building on the Hilltop property, a new 5-8 building on the Canfield Village Middle School site and needed renovation at the high school.
"The high school renovations are included in all three plans," schools Superintendent Joe Knoll said. "The high school needs a new roof, paving, drainage and, if there are funds left over, lights and windows."
Option B is estimated at $107 million and would include the construction of a new K-8 school building on the district's Shields Road property and the high school renovations. It would mean C.H. Campbell, Hilltop and Canfield Village Middle School no longer would be used.
Option C involves a new K-6 school on the Hilltop site and adding a 7-8 grade wing at the high school, along with the high school renovations. The price tag for this option is estimated at about $91 million, according to Knoll.
Each plan's cost is a rough estimate. He said the committee projected a 10 percent increase due to building costs rising.
"We are waiting on the 'cost set' to be more accurate," he said. "The estimated costs could be less -- we just don't know for sure at this time."
Regarding state funding, Knoll said Canfield schools could receive 16 percent of the project cost, but the district would have to wait. It could take years and would be a reimbursement.
Last May, the district's $107.8 million levy proposal for a new pre-K to eighth-grade campus -- a 6.9-mill, 37-year bond levy -- was soundly defeated, with 72 percent of voters opposed.
LENGTHY PROCESS
The three plans came after a process that began last summer.
The district had board of education meetings at each school and residents attending could tour the buildings to see the problems at each location.
This phase wrapped up at the end of last year and a committee of roughly 50 volunteers was formed. Those 50 attended seven sessions starting in January.
The committee has narrowed the choices, and the three were presented on Tuesday at a special open house.
Renee English, the school district's media and communications director, said those who want to remark, but didn't make the meeting, can check out the facilities committee meetings by visiting www.canfieldschools.net and click on "facilities project." There will be a place to send comments to Knoll.
Comments from the open house and from the website will be considered on Thursday when the committee gathers for a final session. Knoll said the hope is to narrow the options to one that will be presented to the board of education at its regular meeting April 19.
Knoll said the board has the final decision on whether to go with that plan, alter it or choose a totally new plan.